Project proposal mgmt 570

In the sections below is some helpful information that will prove valuable with respect to facilitating your completion of a Course Project reflective of the high standards of quality work and personal learning that should be the aim of each participant in the course. Within this broad theme, the project is intended to be an opportunity to explore in some depth a topic related to the course that is of specific significance to you. In developing the project, select a specific conflict situation of interest to you. Think of yourself as a conflict resolution consultant and assume that a key manager has requested a thorough analysis and recommended course of action to resolve an actual conflict that will make a difference to the future performance of the organization.

Project proposal mgmt 570

Centerra argues that the agency failed to evaluate prices on a common basis and erred in not discussing the disparity with Centerra.

In those cases, however, the lack of a common understanding could be traced to unclear or latently ambiguous requirements found within the solicitation, which resulted in offerors proposing differing products or solutions. Here, Centerra has not identified any PWS requirements that are ambiguous or unclear, and has therefore not provided us with a basis to conclude that KBR proposed to meet different PWS requirements from the requirements Centerra proposed to meet.

Instead, Centerra broadly asserts that the staffing and pricing differences, by themselves, evidence that something in the solicitation caused offerors to possess differing understandings of the solicitation requirements.

Indeed, the solicitation permitted offerors to propose their own staffing solutions, so long as they provided the basis for their staffing estimates and explained how such staffing would meet the PWS requirements.

See RFP at See The Gerard Co. We also conclude that the Navy was not otherwise obligated to tell Centerra that its staffing and pricing were high in relation to other offerors. When an agency engages in discussions with an offeror, the discussions must be meaningful, that is, sufficiently detailed so as to lead an offeror into the areas of its proposal requiring amplification or revision.

We do not agree. Indeed, Centerra received a strength for one aspect of its staffing: As discussed above, however, the agency was under no obligation to tell Centerra that its price was comparatively high; we therefore conclude that the agency similarly was not obligated to tell Centerra its high staffing was causing its overall price to be comparatively high.

Centerra also contends that it was misled during discussions into increasing its staffing because the Navy told the firm that its staffing may be low for certain annexes.

AR, Tab 15, at During discussions, agencies may not consciously mislead or coerce an offeror into raising its prices.

NERVOUS SYSTEM DISEASE

We will not find coercion in discussions, however, where an agency in good faith provides accurate information to an offeror about its concern, and provides the offeror with the opportunity to explain or revise its rates.

In response, Centerra provided further explanation and also increased its FTEs by a small number. Sep 11, Piton raises various challenges to the agency's conduct of discussions and its evaluation of price. We first address Piton's contentions that discussions were misleading, and not meaningful.

In this regard, the protester essentially argues that it was unreasonable for the agency to fail to disclose during discussions that it considered Piton's price to be not fair and reasonable, and improper for the agency to ultimately conclude that Piton's price was not fair and reasonable after Piton reduced its price in response to the agency's discussion question.

Protest at 8; Comments at 5. When an agency engages in discussions with an offeror, the discussions must be "meaningful," that is, sufficiently detailed so as to lead an offeror into the areas of its proposal requiring amplification or revision in a manner to materially enhance the offeror's potential for receiving the award.

The requirement that discussions be meaningful, however, does not obligate an agency to spoon-feed an offeror or to discuss every area where the proposal could be improved.

We find no merit to the protester's arguments. The record shows that the agency clearly led Piton to the area of its proposal needing revision by indicating that Piton's total price, as well as its price for a particular labor category, were high.

Project proposal mgmt 570

As such, the agency fulfilled its obligation to conduct meaningful discussions. Additionally, contrary to the protester's assertions, the record also shows that the agency only concluded that Piton's price was not fair and reasonable after evaluating FPRs. Although Piton asserts that it should have received an award because it lowered its pricing in response to the discussion question, the record shows that other proposals from technically-acceptable offerors received awards because they offered lower prices.

In light of the record here, the protester has not shown that the agency's conduct of discussions was unreasonable. Piton Science and Technology B Jul 28, Global Dynamics contends that the Army repeatedly asked it during discussions to raise its prices.

Protester Comments at 3. In conducting discussions with offerors, an agency may not consciously mislead or coerce an offeror into raising its price. However, we will not find discussions to be improper where the agency in good faith provides accurate information to an offeror, even where the offeror uses that information to its ultimate competitive detriment.

The record shows that the agency did not ask the protester to raise its price. Specifically, EDT contends that the agency engaged in improper and misleading discussions.

According to the protester, it was arbitrary for the agency to consider narrative responses more favorably than mere acknowledgments of compliance given that the discussion letter indicated that both would be acceptable.The project management consultant (s) selected to manage the CDBG-DR, DRA and HMGP projects for the County of Cumberland and/or the City of Fayetteville will provide all of the necessary program planning and project management expertise, including provision of on-site.

MGMT Week 7 Course Project Final Managing Conflict in the Workplace This week, your Course Project is due. Optional: Post a copy of the Executive Summary from your Course Project in Doc Sharing. See the Course Project content item under the Course Home section of .

Project proposal mgmt 570

Formulate the management goals that the expenditure would support. Goals may include: revenue, process improvement, productivity, quality improvement, safety, and/or employee development.

Click the button below to add the HSN Week 5 Capital Project Proposal to your wish list. Cyberfriends: The help you're looking for is probably here. This website collects no information. If you e-mail me, neither your e-mail address nor any other information will ever be passed on to any third party, unless required by law.

TutorialRank provides MGMT final exam guides we offer MGMT final exam answers, MGMT week 1,2,3,4,5, individual and team assignments, dq.

Study 16 KELLER MGMT Entire Course flashcards from zan t. on StudyBlue. Study 16 KELLER MGMT Entire Course flashcards from zan t.

on StudyBlue. At the end of Week 3, there is a Course Project Proposal due.

Course Schedule | CBU Online | California Baptist University The files include financial assessments of the worth of real estate and buildings within proposed project areas.
Prince George's Community College :: Search for Continuing Education Courses In doing so, PAE asserts that the agency failed to conduct its evaluation on an equal basis, and had it not considered the excess information, CENTRA would have been assessed significant weaknesses similar to those assigned to its own proposal. The RFP required offerors to provide a maximum two-page resume for each of the 39 proposed personnel, or in lieu of resumes, to submit the information in the form of a table, with the same page limits being applied.
Background Fig-2 First American patent, July 31, Fig.

Please note that your paper cannot be adapted from another class; it must be an original work for this course.

MGMT WEEK 3 COURSE PROJECT PROPOSAL by wise americans on Prezi